Secure Hoarding & Compound Installation
End Client: HM Prison & Probation Service (HMPPS)
Location: HMP Grendon & HMP Springhill
Project Overview
Wildside Limited delivered compound construction and hoarding fencing as part of early enabling works at Grendon & Springfield Prisons. Working within a live custodial environment, the project required strict security, safety compliance, and coordinated operations.
The works established a fully secure compound with controlled access, supporting site logistics, storage, and workforce welfare.
Scope of Works
Wildside delivered a turnkey package including:
• Installation of hoarding fencing to designated perimeter zones
• Construction and installation of vehicular and pedestrian access gates
• Formation of a secure compound area, including:
○ Environmental mitigation controls including GCN and Tree protection
○ Site clearance and preparation
○ Installation of hardstanding / working platform
○ Defined storage and laydown areas
• Integration with existing prison infrastructure and access routes
• Traffic and access management provisions within a restricted environment
Key Challenges
1. Live Prison Environment
Working within an operational prison required:
• Escorting procedures and controlled movement of operatives
• Strict compliance with HMPPS security requirements
• Daily coordination with prison staff and Laing O’Rourke teams
2. Security-Critical Infrastructure
• All fencing and gates required robust installation standards to prevent unauthorised
access
• Interfaces with existing secure boundaries had to be seamless and tamper-resistant
3. Logistics & Access Constraints
• Limited access windows and controlled delivery schedules
• Segregation of construction activities from prison operations
4. Programme Sensitivity
• Works were on the critical path to enable subsequent construction phases
Wildside Solution
Wildside adopted a planned, compliance-led delivery strategy:
- Developed site-specific RAMS and security protocols aligned with HMPPS and Laing O’Rourke requirements
- Implemented phased installation sequencing to maintain operational continuity and meeting temporary Works design
- Utilised experienced supervisors familiar with rail and high-security environments
- Ensured all materials and plant were pre-approved and controlled on entry/exit
Health, Safety & Compliance
• Zero harm approach aligned with CDM 2015
• Full compliance with:
○ Site induction and escorting procedures
○ Tool control and asset tracking
○ Environmental licences and considerations
Programme Delivery
• Works completed on programme, supporting downstream activities
• Flexible working approach to accommodate restricted access windows
• Rapid mobilisation and efficient installation methodology
Outcome & Value Delivered
• Fully secure hoarding and access system installed to client temporary works design and specification
• Operational compound delivered, enabling efficient site setup
• Enhanced site security and controlled access for all subsequent works
• Strengthened working relationship with Laing O’Rourke
Client Feedback
“Wildside demonstrated a proactive and professional approach throughout, delivering secure infrastructure within a highly constrained and sensitive environment while maintaining safety, quality, and programme commitments.”
Key Benefits
• Security Assurance – robust perimeter and access control
• Operational Efficiency – fully functional compound ready for use
• Compliance Confidence – adherence to prison and Tier 1 standards
• Reliable Delivery Partner – experienced in complex environments
Wildside Capability Highlight
This project reinforces Wildside’s capability in:
• High-security environments (custodial / rail / infrastructure)
• Fencing, hoarding, and access control systems
• Enabling works and compound construction
• Working under Tier 1 contractor frameworks